The Queensland subdivision process: from first check to new titles

If Liveproject has given your block a Possible or Strong result, this page sets out the usual next steps in Queensland. Other Australian states use different planning systems.

In Queensland, subdividing land is usually a reconfiguring a lot application under the Planning Act 2016. After an approval there is still engineering and operational works, service connections, infrastructure charges, plan sealing, and lodgement with Titles Queensland.

A Possible or Strong result is a first look, not a council decision. Nothing here is planning, legal, financial or tax advice, and nothing here is a promise that a particular block will be approved.

Subdivision finance · Joint venture development

The steps

Timeframes are indicative. Unless noted, they are statutory periods. They start only when an application is properly made, and they pause or extend if council asks for more information, a state agency is referred, or you agree to more time.

  1. 01

    Check your block

    Start with a Liveproject check of the address. The checker looks at the planning scheme settings that can be read for that lot, such as zone, lot size and frontage, and selected overlays, and returns an Unlikely, Possible, Strong or Unverified result, plus a short explanation. It is a first look, not a development approval and not a substitute for a title search or a planner’s advice.

    Who is involved. You, and Liveproject.

    Typical time. Immediate for the online check. That is a Liveproject product time, not a statutory period.

    How Liveproject helps. This is the first step in the Liveproject Subdivision Guide. The result is a first look, not a council decision.

  2. 02

    Desktop due diligence

    Before you spend money on a full application, confirm what is on the title and what sits on the land. Typical checks include a current title search, a plan search, the zone and overlays, whether the proposal is likely to be code assessable, impact assessable, or in limited cases accepted development, and whether water, sewer, stormwater, electricity and telecommunications appear to be available. Brisbane City Council advises landowners to use City Plan online first, and notes that a town planning consultant is not mandatory but will save time. Moreton Bay points people to its planning scheme and overlay maps, and notes that some zones and high or medium flood or erosion-prone areas have extra requirements.

    Who is involved. You; a conveyancer or solicitor for the title; often a town planner and surveyor for a first advice; your accountant if ownership or tax treatment matters.

    Typical time. No official end-to-end period is published for this step. It depends on how quickly searches come back.

    Sources: Brisbane City Council, Subdividing land · City of Moreton Bay, Reconfiguring a lot

    How Liveproject helps. The Guide gives you a due-diligence checklist and suggested questions for a planner, surveyor or solicitor. It does not carry out a title search or give legal advice.

  3. 03

    Engage a planner and surveyor

    A registered surveyor measures the land and prepares a proposed plan of subdivision. A town planner assesses the proposal against the planning scheme and helps you decide whether to seek pre-lodgement advice. Pre-lodgement is optional. Councils say the advice is not a detailed assessment and not a commitment to approve or refuse.

    Who is involved. Town planner; registered surveyor; you, to give consent later; council officers if you book pre-lodgement. A civil engineer may join if access, stormwater or levels already look tight.

    Typical time. Indicative council service standards: Brisbane aims to meet for a preliminary discussion within 5 working days of fee payment, and for a pre-lodgement meeting within 15 working days. Sunshine Coast schedules a meeting within 15 business days of payment and provides notes within 5 business days. Moreton Bay asks for requests at least 7 business days before the date, and usually schedules meetings within 10 business days of the request. Gold Coast meetings are limited to 45 minutes.

    Sources: Brisbane City Council, Request planning advice · Sunshine Coast Council, Pre-lodgement meeting · City of Moreton Bay, Pre-lodgement advice · City of Gold Coast, Pre-lodgement advice

    How Liveproject helps. The Guide lists what to take to a pre-lodgement meeting, suggested questions, and the official booking page for your council. It can also remind you that pre-lodgement advice is not an approval.

  4. 04

    Prepare and lodge the application

    Most subdivisions that create new lots are assessable development and need a development application to the council. A properly made application under section 51 of the Planning Act 2016 includes the approved form, usually DA Form 1, the consent of all owners, the required plans and supporting material, and the application fee. Applications are code assessable or impact assessable, as set by the planning scheme. Impact assessment must be publicly notified. On the Gold Coast, subdivision is code assessable in all zones if the required lot sizes and relevant overlays can be met; below the stated minimum, the application needs impact assessment.

    Who is involved. Town planner; surveyor; any specialist report authors; you, to sign owner’s consent; council; any referral agency.

    Typical time. Preparing the application is not a statutory period. Once lodged, council has 10 business days to decide whether the application is properly made. If council issues an action notice, you generally have 20 business days to fix the problems.

    Sources: Planning Act 2016, section 51 · Development Assessment Rules guidance, July 2025 · City of Gold Coast, Reconfiguring a lot

    How Liveproject helps. The Guide keeps a lodgement checklist and the official lodgement link for your council. It does not prepare or lodge the application.

  5. 05

    Assessment, decision and conditions

    The Development Assessment Rules have five parts: application, referral, information request, public notification and decision. Not every part applies to every application. If a referral agency applies, the usual assessment period is 25 business days unless a special period is set. You generally have three months to respond to an information request. Public notification, where required, is at least 15 business days, or 30 business days if the application includes a variation request. The decision period is 35 business days for both code and impact applications, plus 5 business days to give the decision notice. Unless the approval states a different period, a reconfiguring a lot approval lapses if the plan is not given to the council within 4 years. Brisbane City Council says a code assessable subdivision that aligns with City Plan can generally take 3 to 4 months at the application stage. That does not include building approval and works.

    Who is involved. Council; any referral agency; your planner; submitters, if the application is impact assessable.

    Typical time. The clocks above are indicative statutory periods. They start when an application is properly made, and they pause or extend if council asks for more information, a state agency is referred, or you agree to more time.

    Sources: Development Assessment Rules · Planning Act 2016, sections 53 and 85 · Brisbane City Council, How we assess development applications

    How Liveproject helps. The Guide explains the formal parts in plain English and suggests questions for your planner if an information request arrives. It does not respond to council on your behalf.

  6. 06

    Operational works and engineering

    A reconfiguring a lot approval is often followed by a separate operational works application for filling, excavation, roadworks, stormwater and other infrastructure. Engineering plans generally need to be certified by a Registered Professional Engineer of Queensland. Read the approval conditions with your engineer and planner before you design or construct anything.

    Who is involved. Civil engineer; often the surveyor; town planner; council; contractors once approvals are in place.

    Typical time. Operational works applications use the same Development Assessment Rules timeframes as other development applications. There is no separate official construction period for a house-lot subdivision, and none is stated here.

    Sources: Brisbane City Council, Operational work application · Development Assessment Rules

    How Liveproject helps. The Guide turns typical approval-condition themes into a checklist and links to your council’s operational works page. It is not an engineering review of your conditions.

  7. 07

    Connect water, sewer, power and telecommunications

    New lots generally need lawful connections, or a confirmed ability to connect, before council will seal the survey plan. Unitywater covers the Sunshine Coast, Moreton Bay and Noosa. Urban Utilities covers Brisbane and several nearby council areas, and a one-into-up-to-three residential subdivision may be eligible for a Standard Connection. The City of Gold Coast is its own water and sewerage provider. Energex generally makes a connection offer within 15 business days of a completed application in its network area. For a small two-lot residential development, nbn says you should allow a minimum of three months’ notice before service connections are required. nbn will endeavour to meet that period but does not guarantee it.

    Who is involved. Your civil engineer and surveyor; the water authority or an accredited contractor; an Energex-accredited consultant; a telecommunications designer; council for driveway and crossover works.

    Typical time. Utility timeframes are those published by each provider. They are not a single council clock.

    Sources: Unitywater, Subdivisions · Urban Utilities, Standard connections · Energex, Subdivision connections · nbn, New developments

    How Liveproject helps. The Guide points you to the right water authority for your council, plus Energex and telecommunications pages, and a services checklist for plan sealing. It does not design or book connections.

  8. 08

    Pay infrastructure charges

    Infrastructure charges help fund trunk infrastructure. The charge is set in the council’s resolution and must not exceed the State maximum. From 1 July 2026 that maximum is A$27,163.80 for each dwelling with 2 or fewer bedrooms and A$38,029.25 for each dwelling with 3 or more bedrooms. These figures are a cap, not a quote. Each council sets its own adopted charge up to that maximum. In South East Queensland the cap is shared with the water distributor-retailer. Credits and indexation can change the bill. Councils generally require the charges to be paid before the survey plan is sealed. A bond for uncompleted works does not usually defer infrastructure charges.

    Who is involved. Council infrastructure charges officer; the water authority where it bills its share; your planner or accountant; your solicitor if charges are paid from a sale.

    Typical time. The due date is set in the infrastructure charges notice and the approval conditions. It is commonly before plan sealing.

    Sources: Queensland Government, Infrastructure charges · Planning (Prescribed Amounts) Amendment Regulation 2026

    How Liveproject helps. The Guide explains that the State figure is a maximum, and lists questions to ask about credits, indexation and the payment date. It will not estimate your charge or treat the cap as the bill.

  9. 09

    Survey plan sealing

    When the works and conditions are complete, or when remaining works are properly bonded where the council allows it, a registered surveyor lodges the final plan with council. This is plan sealing under Schedule 18 of the Planning Regulation 2017. You need a sealed plan to create new land titles.

    Who is involved. Registered surveyor; solicitor or conveyancer; council plan sealing officers; the water authority and other service providers.

    Typical time. Council has 20 business days to decide a properly made request. Moreton Bay’s accredited path is described by council as allowing approval within 5 business days for a properly made application. Sunshine Coast first advises fees within 5 business days, then runs the 20-business-day assessment.

    Sources: Planning Regulation 2017, Schedule 18 · Sunshine Coast Council, Plan sealing · Brisbane City Council, Plan sealing requests · City of Gold Coast, Plan sealing

    How Liveproject helps. The Guide provides a plan-sealing document checklist, the official lodgement link for your council, and a reminder that a sealed plan has a limited life before it must be lodged with Titles Queensland.

  10. 10

    Lodge with Titles Queensland

    Once council has sealed the plan, it is lodged with Titles Queensland so new titles can be created. Sunshine Coast, Brisbane and Gold Coast state that you have 6 months from council approval to lodge. If that window is missed, the approval lapses and you have to go back to council. Indicative Titles Queensland fees for 2026/27, not subject to GST, are $496.12 for lodging a plan of survey plus $36.49 for each lot or interest, and $94.42 for each new indefeasible title. Use the Titles Queensland fee calculator for a particular lodgement.

    Who is involved. Solicitor or conveyancer; registered surveyor; Titles Queensland.

    Typical time. The 6-month lodgement window is the official limit on the sealed plan. Titles Queensland does not publish a registration turnaround on the pages reviewed, so none is stated here.

    Sources: Titles Queensland fees, 2026/27 · Titles Queensland fee calculator

    How Liveproject helps. The Guide reminds you of the 6-month window once you record the sealing date, and links to the official fee calculator. Your solicitor or surveyor still prepares and lodges the documents.

  11. 11

    Sell, build or hold

    Once new titles are issued, you can sell a lot, build on it, or hold it, subject to the planning scheme, any conditions that still run with the land, and any easements or covenants. Building a dwelling is a separate process. Questions about how a project might be paid for, or about a development partner, are covered on the companion pages. Liveproject does not offer credit, suggest a particular credit product, or act as a credit licensee.

    Who is involved. You; your solicitor or conveyancer; your accountant; a development partner only if you choose to explore that path.

    Typical time. No official period applies to this step.

    How Liveproject helps. The Guide points you to the finance and joint venture pages. It does not recommend a credit product, a partner, or a financial outcome.

Who you’ll need

For a straightforward one-into-two, a town planner and a registered surveyor are usually the first appointments. Others join as the site and the conditions require. Liveproject does not recommend a named firm on this page.

  • Town planner. Interprets the planning scheme, prepares the development application, and helps you read the conditions. Expert help is not mandatory, but Brisbane City Council notes that it will save time.
  • Registered surveyor. Surveys the land and prepares the plan for sealing and Titles lodgement.
  • Civil engineer. Designs operational works such as access, earthworks and stormwater. Brisbane requires RPEQ certification on engineering plans.
  • Solicitor or conveyancer. Title due diligence, owner’s consent, easements, and lodgement with Titles Queensland.
  • Accountant. Ownership, GST, duty and how the project sits in your affairs. That advice comes from them, not from Liveproject.
  • Development partner. Only if you choose to explore that path. See the joint venture page. Liveproject does not name a firm here.

Indicative cost categories

There is no official typical total for subdividing a house lot in Queensland, and this page does not invent one. Amounts below are indicative and can change.

  • Professional fees for a planner, surveyor, engineer and solicitor. Ask each one for a written proposal.
  • Council application fees, set in each council’s register. As one Sunshine Coast 2026/27 example only, a reconfiguration of up to five lots is a base of $2,755 plus $1,100 per lot. For six lots or more the base in that register is $1,925 plus $1,100 per lot.
  • Infrastructure charges, up to the State maximum of A$27,163.80 for a dwelling with 2 or fewer bedrooms or A$38,029.25 for 3 or more bedrooms, from 1 July 2026. The maximum is not the bill for a particular site.
  • Service connections. nbn’s published developer contribution is capped at $600 including GST per house lot and $400 including GST per unit, determined on application. A separate end-user contribution of up to $300 including GST may also apply.
  • Plan sealing. As one Sunshine Coast 2026/27 example only, $680 per lot, with a minimum of $1,295.
  • Titles Queensland lodgement. See the fees in step 10, and use the official fee calculator.

Questions

Do I always need a development application to subdivide?

Usually yes, if you are creating new lots. Some limited types are accepted development and do not need a development application. Brisbane lists merging existing lots and certain building format plans. Moreton Bay says amalgamating lots does not require council approval. Your planner or surveyor should confirm the path for your land.

How long does a subdivision take in Queensland?

There is no single official end-to-end period. The Development Assessment Rules set clocks for the application itself, including a 10-business-day confirmation period and a 35-business-day decision period, which pause or extend if more information or a referral is required. Brisbane City Council says a code assessable subdivision that aligns with City Plan can generally take 3 to 4 months at the application stage, not including building approval and works. After approval you still need operational works, service connections, plan sealing and Titles lodgement.

What is the difference between code assessment and impact assessment?

The planning scheme sets the category. Code assessment is assessed against the relevant codes and does not require public notification. Impact assessment is a broader assessment and must be publicly notified. On the Gold Coast, a subdivision that meets the minimum lot size is generally code assessable; one that does not is impact assessable.

How long is a subdivision approval valid?

Unless the approval states a different period, a reconfiguring a lot approval lapses if the plan is not given to the local government within 4 years after the approval starts to have effect. Once the plan is sealed, you then have 6 months to lodge it with Titles Queensland.

Is the state infrastructure figure the amount I will pay?

No. From 1 July 2026 the State maximum for a dwelling with 3 or more bedrooms is A$38,029.25, and A$27,163.80 for a dwelling with 2 or fewer bedrooms. Each council adopts a charge up to that cap. In South East Queensland the cap is shared with the water distributor-retailer. Credits, indexation and the details of your notice all affect the amount. Treat the State figures as a ceiling, not a quote.

What is plan sealing, and when can I get new titles?

Plan sealing is council’s approval of the survey plan, after conditions are met or remaining works are bonded where that is allowed. New titles are created only when the sealed plan is registered with Titles Queensland, within 6 months of council’s approval.

Where do finance and a joint venture fit?

They can be considered during due diligence, after an approval, before works, or after new titles. The subdivision finance page covers the main ways people pay for a subdivision. The joint venture page explains a development-partner path. Liveproject does not provide financial advice or arrange credit.

Does Liveproject lodge the application or guarantee an approval?

No. Liveproject provides a first-look checker and general information, including the optional free Liveproject Subdivision Guide. A Possible or Strong result is not a council decision.

General information only

This page is general information about the usual Queensland process for reconfiguring a lot. It is not planning advice, legal advice, financial advice, tax advice or a credit guide. It is not an assessment of any particular property and it is not a development approval.

Planning schemes, fees, charges and statutory timeframes change. Figures and periods on this page are indicative and were drawn from public official sources current as at 25 November 2026. Liveproject is a service of Combine TRS Pty Limited (ABN 42 112 983 678).