Infrastructure charges are the public-works share of a subdivision. Three layers usually show up: the state maximum, the charge the council has adopted, and the distributor-retailer's share. Running this screen does not create a charge.
State maximum
From 1 July 2026, Schedule 16 of the Planning Regulation 2017 caps adopted charges at A$38,029.25 for a dwelling of three or more bedrooms and A$27,163.80 for one or two bedrooms. Councils adopt their own resolutions under that cap.
Who bills the water share
- Unitywater on the Sunshine Coast and in Moreton Bay. The published residential-lot share observed on 24 Nov 2026 is A$16,368.60 and A$14,233.57. Distributor share only.
- Urban Utilities across Brisbane, Ipswich, Lockyer Valley, Scenic Rim, and Somerset.
- City of Gold Coast for its own water business.
- Logan and Redland have their own water businesses. Read the current resolution before relying on a figure.
Adopted charges change. The checker does not calculate one for your lot.
Questions people ask
Does this page quote a price to subdivide?
No. It explains the kinds of costs that usually appear, and it cites the published state cap and distributor figures with their sources. Combine TRS does not quote a job.
What is the Schedule 16 cap?
From 1 July 2026 the Planning Regulation 2017 Schedule 16 sets maximum adopted charges. A council can adopt less. The cap is not the charge that will apply to a particular block.
Are Unitywater figures the whole infrastructure charge?
No. The Unitywater amounts cited here are the distributor share for a residential lot, observed on the official schedule on 24 Nov 2026. Council charges and works are separate.
The state maximum
Schedule 16 of the Planning Regulation 2017 sets the maximum adopted charge. From 1 July 2026 that maximum is A$38,029.25 for a dwelling of three or more bedrooms and A$27,163.80 for a dwelling of one or two bedrooms. Councils adopt a resolution under the cap. Some adopt the cap. Some adopt less, or different figures by area. The resolution in force when the charge is levied is the one that matters, not a blog from a previous financial year.
The adopted charge is for trunk infrastructure. It is not the council's application fee, and it is not the quote for the reticulation you build inside the subdivision. People add those three numbers together and then argue about which one was 'the charge'. Keep them in separate columns.
Council and distributor
In distributor-retailer areas the water and wastewater share is billed by the distributor. Unitywater covers the Sunshine Coast, Moreton Bay, and Noosa. The residential-lot shares observed on 24 Nov 2026 were A$16,368.60 and A$14,233.57 respectively, and they are only that share. Urban Utilities covers Brisbane, Ipswich, Lockyer Valley, Scenic Rim, and Somerset and publishes its own schedule. City of Gold Coast, Logan, and Redland are not in those two distributors. Their water business is the council's.
Gympie, Bundaberg, and Toowoomba are outside those south-east distributor boundaries. Their infrastructure charging instruments are council documents. Do not paste a Unitywater share onto a Gympie notice.
Credits, offsets, and when you pay
An existing lawful lot can attract a credit so that the charge is for the additional demand, not for the lot that already exists. The credit rules are in the charges resolution. They are technical, and they depend on the existing use. Assuming a full credit because 'there is already a house' is a common mistake.
Offsets and refunds arise when the applicant builds trunk works instead of paying, or builds more than their own share. They are negotiated against the council's infrastructure plan, not against a neighbour's story. Payment is commonly required before the survey plan is sealed. A decision notice that is silent in your memory is rarely silent on the page. Read the conditions before you book the sealing lodgement.
What this site will not calculate
The checker can show whether a public water or sewer main is mapped within 80 metres for Unitywater and Urban Utilities areas. That proximity is not a charge, not a connection, and not spare capacity. The charges guide stops at explaining the instruments. The notice for a real application comes from the council and, where relevant, the distributor.
Levies are commonly collected before the survey plan is sealed, which is later than lodgement and earlier than the new titles. An applicant who has paid the application fee and the consultant, and who has not yet read the charges condition, is not finished with the public bill. Ask for the adopted resolution and the distributor schedule for the same financial year, and match the charge category to the dwelling the resolution describes, not to the house that happens to be next door.
If the proposal changes the number of bedrooms, or replaces a house with something the resolution treats as a different use, the credit for the existing lot can shrink or disappear. That is why a charges estimate made before the design is settled should be labelled as provisional. Nothing on this page is that estimate. Trunk charges and the pipes you construct inside the subdivision remain different ledgers even when both are discussed in the same meeting with the council and the distributor.