There is no single South East Queensland minimum lot size. Each planning scheme sets its own, and a neighbourhood plan, precinct, slope band, or overlay can move it. The figures below are the ones commonly cited from the operative schemes. They are indicative. Confirm them on the council map before you rely on them.
| Council | Indicative position, cited from published scheme summaries |
|---|---|
| Sunshine Coast | Planning Scheme 2014, Table 9.4.4.3.2 is commonly cited at 600 m² on slopes up to 15%, 1,000 m² at 15–20%, and 1,500 m² above 20%. Local plans can raise that. Buderim documents cite 700 m² in places, and BUD LPP-1 can switch a proposal to impact assessment. |
| Moreton Bay | Suburban neighbourhood lots are commonly cited at 600 m² with 12.5 m frontage. Next generation neighbourhood is often a 10–25 lots per hectare density band rather than one minimum. Emerging community and interim precincts can restrict a simple split. |
| Brisbane | City Plan 2014 fact sheet: low density residential is typically 450 m² for a front lot and 600 m² for a rear lot. Around qualifying centres, smaller lots of 400 m² and 300 m² are described. Neighbourhood plans can change the answer. |
| Logan | Planning Scheme 2015 ROL table is commonly cited as small lot 300 m², suburban 400 m², village 500 m², large suburban 1,000 m², small acreage 2,000 m², and acreage 4,000 m². Rear lots are allowed in some precincts only. |
| Gold Coast | City Plan is process-led: zone, residential density, minimum lot size overlay, and ridges and significant hills, then Part 5.6. Published commentary often cites 600 m² in low-density areas, subject to the density overlay. |
| Ipswich | City Plan 2025 sets size by the mapped lot type on the OV6 building height and density overlay, not the zone label alone. Published scheme notes describe established suburban at 450–2,000 m², new suburban at 300 m², and large lot at 2,000 m² serviced or 4,000 m² unsewered. |
| Redland | City Plan version 14 notes describe low density residential at 400 m² and 10 m, with precincts at 2,000 m², 6,000 m², and 1,600 m² on Kinross Road. Rear-lot net area excludes the accessway. |
| Noosa | Noosa Plan 2020 is restrictive. A large lot is not, by itself, a candidate. Read the zone and the flood and biodiversity overlays. |
| Scenic Rim | Minimum and average lot sizes both matter. Much of the freehold stock is rural or rural residential, including a large hectare share. |
| Lockyer Valley | Rural and rural-residential minimums dominate, with flood a usual watchout in the Lockyer catchment. Confirm the operative table. |
| Somerset | Rural and township rules dominate, with flood along the Brisbane Valley a usual watchout. Confirm the operative table. |
The 1,000 m² and 1,600 m² bands on this site are our own screen. They are not these scheme minimums.
Questions people ask
Is there one Queensland minimum lot size?
No. Each planning scheme sets its own minimum, and a precinct, slope band, or neighbourhood plan can change it. The 1,000 m² figure on this site is a screen we use, not a council rule.
Why do average and minimum both appear?
Some codes require both a minimum area and an average across the new lots. Meeting the minimum on one lot can still fail the average. Read the table for the zone, not a single number from a fact sheet.
Zone, precinct, and the number people quote
There is no Queensland-wide minimum lot size. A council scheme sets a zone, and often a precinct or local plan inside that zone, and the acceptable outcome for lot size lives in that more specific layer. Quoting '600 square metres' for a whole city erases the precinct that says 400, the slope row that says 1,000, and the neighbourhood plan that says something else again. The 1,000 m² and 1,600 m² bands on this site are our own screen for whether a lot is even large enough to talk about. They are not those scheme numbers.
Average lot size and minimum lot size are also different tests. Some rural-residential codes require both: every proposed lot above a minimum, and the proposal as a whole above an average. Meeting the minimum on the new lot can still fail the average. Rear lots add a third test when the scheme excludes the access strip from the area that counts.
South-east schemes people actually open
Sunshine Coast Planning Scheme 2014 is commonly read with a slope-tiered low density table: about 600 m² to 15 percent, 1,000 m² from 15 to 20 percent, and 1,500 m² above that, with local plans able to raise the figure. Buderim documents have cited about 700 m² in places, and a local plan precinct can change the level of assessment. Moreton Bay's suburban neighbourhood is often cited at 600 m² and 12.5 m frontage, while next generation neighbourhood is frequently a density band of about 10 to 25 lots per hectare rather than one minimum. Emerging community and interim precincts can block a simple split.
Brisbane City Plan 2014's public fact sheet describes low density residential as typically 450 m² for a front lot and 600 m² for a rear lot, with smaller figures near some centres, and neighbourhood plans that override the general position. Logan Planning Scheme 2015 publishes a spread from small lot through suburban, village, large suburban, and acreage precincts, roughly 300 m² up to 4,000 m², and rear lots only in some precincts. Gold Coast City Plan sends you to the zone, the residential density designation, the minimum lot size overlay, and the ridges and significant hills overlay before Part 5.6. Published commentary often mentions 600 m² in low density areas, subject to that density overlay.
Redland City Plan's low density residential standard is often described at 400 m² and 10 m, with precincts at 1,600 m², 2,000 m², and 6,000 m², and the accessway left out of rear-lot net area. Noosa Plan 2020 is tighter than a size table suggests: a large lot is not, by itself, a candidate. Ipswich City Plan 2025 puts size on the mapped lot type in the building height and density overlay, with published notes describing established suburban, new suburban, and large-lot bands. No open zone service was verified for Ipswich, so the checker says the zone needs a manual read.
Gympie, Bundaberg, and Toowoomba
Gympie Regional Council Planning Scheme 2013 is read live from the council's town-planning feature service, including a precinct layer. The zone name on the snapshot is the label in that service. The minimum for a new lot is in the scheme codes, not in a single Gympie number this site is willing to invent. Bundaberg Regional Council Planning Scheme 2015 is read from the adopted zoning service, which can return a zone, a precinct, and a plan-lot reference. Toowoomba Regional Planning Scheme is read from the council map service. The city grid and the rural towns are not the same control, even when both return a zone name.
Scenic Rim, Lockyer Valley, and Somerset stay on a manual zone check because a current open feed was not verified. Their stock is heavily rural and rural residential, so hectare minimums and averages are the usual conversation. Confirm the operative table rather than borrowing a suburban figure from Brisbane or the Sunshine Coast.
Frontage and slope sit beside area
A lot can clear an area figure and still fail a frontage, depth, or slope test. Sunshine Coast's slope tiers are the clearest published example. Gold Coast's minimum lot size overlay is another: the zone name and the overlay value are read together. Battle-axe handles consume land that some schemes then refuse to count. The geometry on a full report from this site is an indicative cadastre measurement. A surveyor still certifies the dimensions that go on a plan.
Use the council hub for the scheme name and the water authority, then the suburb page for the local lot-size mix. The counts there are freehold area on 24 Nov 2026. A suburb with thousands of large lots can still be a poor place to create a new lot if the zone minimum is an acreage figure.