A Queensland subdivision bill is a stack of separate items. Application fees, infrastructure charges, survey, planning work, civil works, plan sealing, and new titles each sit with a different body. This page explains that stack. It does not quote a job for Combine TRS.
The state cap from 1 July 2026
The Planning Regulation 2017 Schedule 16 sets maximum adopted charges. From 1 July 2026 the published maximum is A$38,029.25 for a dwelling of three or more bedrooms and A$27,163.80 for a dwelling of one or two bedrooms. A council can adopt a lower charge. The cap is not the figure that will apply to a particular block.
Distributor shares are only one slice
Unitywater's published residential-lot share, observed on the official schedule on 24 Nov 2026, is A$16,368.60 on the Sunshine Coast and A$14,233.57 in Moreton Bay. Those amounts are the distributor share only. Council charges and construction sit on top.
A published Brisbane example, not our figure
Brisbane Planning Consultants published a worked example of a straightforward Brisbane 1-into-2 at A$108,255 including GST. That page was fetched on 24 Nov 2026. It is their example, not a Combine TRS quote, and it is not a Queensland average.
Across the 11 SEQ council areas, the Queensland cadastre counted 305,778 freehold lots of 1,000 m² or more on 24 Nov 2026, and 223,132 of 1,600 m² or more. Those counts are not a list of lots that can be split, and they say nothing about cost.
Questions people ask
Does this page quote a price to subdivide?
No. It explains the kinds of costs that usually appear, and it cites the published state cap and distributor figures with their sources. Combine TRS does not quote a job.
What is the Schedule 16 cap?
From 1 July 2026 the Planning Regulation 2017 Schedule 16 sets maximum adopted charges. A council can adopt less. The cap is not the charge that will apply to a particular block.
Are Unitywater figures the whole infrastructure charge?
No. The Unitywater amounts cited here are the distributor share for a residential lot, observed on the official schedule on 24 Nov 2026. Council charges and works are separate.
Separate bills
A subdivision budget is a stack, not a single quote. Town planning and the development application, the cadastral survey and later plan sealing, infrastructure charges, civil works, electrical and communications, and the legal work to register titles are paid to different people at different times. Combining them into one 'typical' total is how owners get surprised. This page names the buckets. Combine TRS does not quote a job, and a third-party example is labelled as theirs.
From 1 July 2026 the Planning Regulation 2017 Schedule 16 maximum adopted charge is A$38,029.25 for a dwelling of three or more bedrooms and A$27,163.80 for one or two bedrooms. A council can adopt less. The cap is not the notice you will receive, and it does not include the construction in the street or on the lot.
Planning, survey, and sealing
The planning fee is the council's lodgement charge plus the consultant who writes the report and manages information requests. A code-assessable suburban split and an impact-assessable acreage proposal are not the same amount of work. Information requests, referral responses, and changes to the plan all add time and fees that a first estimate often misses.
The surveyor usually works twice: an identification or detail survey to design against, and the plan of subdivision that is sealed and lodged. Sealing itself can attract a council fee. Title registration, and any document the mortgagee has to sign, sit with the solicitor or conveyancer at the end. If there is no mortgage, that last consent step is simply absent.
Infrastructure charges
Unitywater's published residential-lot share, read from the official schedule on 24 Nov 2026, is A$16,368.60 on the Sunshine Coast and A$14,233.57 in Moreton Bay. That is the distributor share only. Council charges sit beside it. Urban Utilities publishes its own share for Brisbane, Ipswich, Lockyer Valley, Scenic Rim, and Somerset. Gold Coast, Logan, and Redland run their own water businesses. Gympie, Bundaberg, and Toowoomba adopt their own resolutions. None of those documents is calculated by this checker.
Brisbane Planning Consultants published a worked example of a straightforward Brisbane one-into-two at A$108,255 including GST. The page was fetched on 24 Nov 2026. It is their example of one case, not a Queensland average and not a figure from Combine TRS.
Works on the ground
Civil works are the pipes, the driveway, the stormwater, and any road widening the conditions require. A rear lot often needs a constructed handle, sewer and water extended along it, and a crossover that meets sightline rules. A corner lot can look easier for frontage and harder for services and crossovers. Electrical and communications connections are a separate contractor from the civil crew.
On-site effluent, where reticulated sewer is not available, replaces a connection charge with a design and an irrigation area that consumes land. That land then may not count toward the lot size you thought you had. The map layer that says a sewer main is within 80 metres is not a connection approval and not a price.
Pay the adopted charge when the decision notice says so, which is often before the plan is sealed, and keep the planning fees, the survey, and the civil contract in different lines of the budget so a change in one does not get described as a change in all of them.